Skip to content

The Custom Home Building Process Explained: From Lot to Move-In

Building a custom home follows a predictable sequence of phases, from lot selection and feasibility through design, engineering, permitting, construction, and move-in. The full process typically takes 14 to 24 months depending on complexity, site conditions, and local permitting timelines. In the Bay Area, where seismic requirements, hillside grading, and municipal review processes add unique challenges, working with a design-build firm streamlines coordination and keeps the project on schedule. Custom Home's two-phase process separates design from construction so every decision, material, and cost is locked in before ground breaks.

What are the steps to building a custom home?

The custom home building process follows these major phases: lot selection and feasibility (1-6 months), design and architecture (2-4 months), engineering and permits (2-6 months), site preparation and foundation (3-6 weeks), framing (4-8 weeks), mechanical rough-in (4-6 weeks), finishes and fixtures (6-12 weeks), final inspections (2-4 weeks), landscaping, and move-in. Total timeline ranges from 14 to 24 months depending on complexity and location.

Building a Custom Home: The Complete Process

Building a custom home is one of the most rewarding investments you can make. It is also one of the most complex. Unlike buying an existing home or even doing a major renovation, a custom home starts from nothing. Every decision, from the shape of the foundation to the finish on the cabinet hardware, must be made deliberately and in the right order.

Understanding the full process before you begin is the single best thing you can do to protect your budget, your timeline, and your sanity. This guide walks through every phase of building a custom home, from finding the right lot to the day you move in. It covers what happens at each step, how long it takes, and where projects go wrong when homeowners are not prepared.

If you are considering a custom home in the Bay Area, the process described here reflects real-world timelines for cities like San Jose, Los Gatos, Saratoga, Palo Alto, Cupertino, and surrounding communities.

Timeline Overview: Every Phase at a Glance

Before diving into the details, here is a high-level view of the entire custom home building process with typical durations:

PhaseDurationCumulative Timeline
Lot Selection and Feasibility1-6 monthsMonths 1-6
Design and Architecture (Phase 1)2-4 monthsMonths 3-8
Engineering and Structural Plans1-2 monthsMonths 5-10
Permitting and Plan Review2-6 monthsMonths 7-14
Site Preparation and Grading2-4 weeksMonths 14-15
Foundation2-4 weeksMonths 15-16
Framing and Structural Shell4-8 weeksMonths 16-18
Mechanical Rough-In (MEP)4-6 weeksMonths 18-19
Insulation, Drywall, and Exterior3-5 weeksMonths 19-20
Interior Finishes and Fixtures6-12 weeksMonths 20-23
Final Inspections and Punch List2-4 weeksMonths 23-24
Landscaping and Exterior Finishes2-6 weeksOverlaps with above
Move-In1-2 weeksMonth 24

These timelines overlap in practice. Engineering can begin while design is wrapping up. Landscaping often runs in parallel with interior finishes. The cumulative column reflects a realistic worst-case scenario; well-managed projects can compress this timeline significantly.

Phase 1: Lot Selection and Feasibility Study

Finding the Right Lot

Everything begins with the land. The lot you choose dictates what you can build, what it will cost, and how long it will take. In the Bay Area, lot selection is especially consequential because of variable terrain, seismic zones, and municipal zoning rules that differ from city to city.

When evaluating a lot, consider:

  • Zoning and setbacks. Every city defines what can be built on each parcel: maximum height, floor area ratio (FAR), setback distances from property lines, and allowed uses. A lot zoned R1-8 in San Jose has very different constraints than one zoned R1-10 in Saratoga.
  • Topography. Flat lots are the simplest and most cost-effective to build on. Hillside lots in areas like Los Gatos, Saratoga, and Woodside require retaining walls, special foundations, and additional engineering, often adding 15-30% to construction costs.
  • Soil conditions. The Bay Area has areas with expansive clay, fill soil, and liquefaction zones. A geotechnical (soils) report tells you what the ground can support and what foundation design is needed.
  • Utilities. Confirm that water, sewer, gas, and electrical connections are available at the property line. Bringing utilities to a remote lot can add tens of thousands of dollars.
  • Tree preservation. Many Bay Area cities protect heritage or significant trees. Removing a protected tree requires a permit and sometimes mitigation planting, which can affect your building footprint.

The Feasibility Study

Before purchasing a lot (or before committing to a design direction on a lot you already own), a feasibility study answers the critical question: can you build what you want on this specific piece of land, and what will it cost?

A good feasibility study includes:

  • Zoning analysis and maximum buildable area
  • Preliminary site plan showing building placement
  • Soils report review (or recommendation to order one)
  • Utility availability assessment
  • Identification of any special conditions: flood zones, easements, environmental constraints
  • Preliminary cost range based on site conditions

At Custom Home, we encourage clients to involve us before closing on a lot. We have seen buyers purchase beautiful hillside properties only to discover that grading, retaining walls, and special foundations would add $200,000 or more to their construction budget. A feasibility study costs a fraction of that and can save you from a costly mistake.

Phase 2: Design and Architecture

Why Design is the Most Important Phase

The design phase is where your home is “built” for the first time, on paper and in 3D renderings. Every decision you make during design affects cost, buildability, and how you will live in the finished home. This is also where the most value is created, or lost.

The biggest mistake homeowners make is rushing through design to get to construction faster. Incomplete or underdeveloped design leads to change orders during construction, which are the number one cause of budget overruns and timeline delays in custom home projects.

What Happens During Design

A comprehensive design phase covers:

  • Programming and space planning. Your design team interviews you about how you live: how many people, daily routines, entertaining style, work-from-home needs, future plans. This becomes the program that drives every layout decision.
  • Schematic design. Rough floor plans and exterior massing that establish the home’s overall size, shape, and relationship to the lot. Multiple options are typically presented.
  • Design development. The selected schematic is refined into detailed floor plans, elevations, sections, and interior layouts. Room sizes are finalized. Window and door locations are set. The home’s architectural character takes shape.
  • 3D visualization. At Custom Home, every project gets full 3D renderings so you can see your home from every angle, walk through rooms virtually, and understand spatial relationships before anything is built. This is a core part of our Phase 1 process.
  • Material selections. Flooring, countertops, cabinetry, tile, fixtures, hardware, paint colors. Every material is chosen and priced during design, not during construction. This is what eliminates surprises.
  • Itemized scope of work. A complete line-item budget that shows what everything costs. Not a lump sum estimate, but a transparent breakdown where you can see the cost of each component and make informed trade-offs.

Custom Home’s Phase 1 Process

Custom Home separates the design phase into its own distinct engagement called Phase 1. This is deliberate. Phase 1 has its own scope, its own deliverables, and its own fee. You are not committing to a construction contract when you start design.

Phase 1 deliverables include:

  • Complete 2D floor plans and elevations
  • Full 3D renderings (interior and exterior)
  • Material and finish selections with pricing
  • Itemized scope of work with per-item costs
  • Engineering coordination
  • Preliminary permit strategy

When Phase 1 is complete, you know exactly what your home will look like, exactly what it will cost, and exactly how long it will take to build. Only then do you decide whether to proceed to Phase 2 (construction). There is no pressure, no ambiguity, and no hidden costs.

Phase 3: Engineering and Structural Plans

Why Engineering Cannot Be Skipped

Once the architectural design is finalized, engineers translate your vision into buildable reality. Engineering drawings specify the structural systems that will keep your home standing for decades, through earthquakes, wind, and the daily stresses of use.

In the Bay Area, engineering is especially critical because of seismic requirements. California’s building code mandates specific structural standards for earthquake resistance, and Bay Area jurisdictions enforce these rigorously.

Types of Engineering Required

A custom home typically requires:

  • Structural engineering. Steel beams, wood framing connections, shear walls, hold-downs, foundation reinforcement. The structural engineer specifies every element that resists gravity and lateral (earthquake) forces.
  • Civil engineering. Grading plans, drainage plans, stormwater management, and utility connections. Required for any project that modifies the site.
  • Geotechnical engineering (soils report). Analysis of soil type, bearing capacity, and potential hazards like liquefaction or expansive clay. The geotechnical engineer recommends the foundation type.
  • Title 24 energy compliance. California’s energy code requires detailed calculations proving the home meets energy efficiency standards. This includes insulation values, window performance, HVAC efficiency, lighting, and in many cases, solar panel requirements.
  • Mechanical, electrical, and plumbing (MEP) plans. Detailed layouts showing where every duct, wire, pipe, and fixture will be located.

Engineering Timeline

Engineering typically runs 4 to 8 weeks after architectural plans are finalized. Some engineering work can begin in parallel with late-stage design development. The geotechnical report should be ordered early, ideally during the feasibility phase, since it takes 3-4 weeks and its findings influence foundation design.

Phase 4: Permitting and Plan Review

Permitting is often the least predictable phase of the custom home process. You are submitting your plans to the local building department for review, and their timeline is outside your control.

What you submit typically includes:

  • Architectural plans (floor plans, elevations, sections, details)
  • Structural engineering drawings
  • Civil engineering (grading and drainage plans)
  • Title 24 energy compliance documentation
  • Soils report
  • Any special studies required (arborist report, stormwater management plan, etc.)

Timelines by Bay Area City

Permitting timelines vary dramatically across the Bay Area:

CityTypical Plan Review Timeline
San Jose4-8 weeks
Cupertino6-10 weeks
Fremont4-8 weeks
Los Gatos8-16 weeks
Saratoga10-20 weeks
Palo Alto10-20 weeks
Atherton12-24 weeks
Woodside10-16 weeks

These are estimates and can shift based on the jurisdiction’s workload, the complexity of your project, and whether your plans trigger additional review (design review, environmental review, or neighborhood notification).

Plan Check Corrections

Most first submissions receive plan check corrections. These are questions, requested revisions, or additional documentation that the reviewer wants before approving the permit. Plan check corrections are normal and expected. A well-prepared submittal package minimizes corrections, but even the best plans usually get at least one round of comments.

Custom Home manages the entire permit process for our clients. We prepare the submittal, respond to plan check comments, coordinate with the reviewing agencies, and keep the process moving. Our familiarity with Bay Area building departments helps us anticipate common issues and address them in the original submittal.

Phase 5: Site Preparation and Grading

Preparing the Land

Once permits are approved, construction begins with site preparation. This is the transition from paper to physical reality.

Site preparation includes:

  • Demolition (if there is an existing structure being replaced)
  • Tree protection for any trees that will be preserved
  • Rough grading to establish the building pad elevation and drainage patterns
  • Erosion control measures as required by local ordinances
  • Utility trenching to bring water, sewer, gas, and electrical to the building location
  • Temporary facilities including construction fencing, portable restrooms, and a dumpster

For flat lots in established neighborhoods, site preparation may take as little as one to two weeks. Hillside lots with significant grading, retaining walls, or rock removal can take four to six weeks or more.

Soil and Grading Inspections

The building department inspects the site at this stage to verify that grading matches the approved plans and that soil conditions align with the geotechnical report. If unexpected soil conditions are found (which is more common on hillside sites), the geotechnical engineer may need to revise foundation recommendations, which can add time.

Phase 6: Foundation

The Base of Everything

The foundation is the most structurally critical component of your home. In the Bay Area, foundation types are dictated by soil conditions, seismic requirements, and the building’s size and weight.

Common foundation types for Bay Area custom homes:

  • Slab-on-grade. A concrete slab poured directly on prepared soil. Cost-effective for flat lots with stable soil. Often includes radiant heating tubing embedded in the slab.
  • Raised (stem wall) foundation. Concrete footings with short walls that create a crawl space beneath the first floor. Common in the Bay Area and preferred for sloping sites or areas with drainage concerns.
  • Deepened footings or piers. Required in areas with poor bearing soil, liquefaction potential, or steep slopes. Piers can extend 10 to 30 feet or more to reach stable bearing material.
  • Basement foundation. Less common in California but used on hillside lots where the downhill side creates natural basement conditions.

Foundation Construction Sequence

  1. Excavation to the depths specified in the structural plans
  2. Formwork installation (wood or steel forms that define the shape of the concrete)
  3. Rebar placement per structural engineering specifications
  4. Inspection by the building department (pre-pour inspection)
  5. Concrete pour
  6. Curing time (typically 7 days minimum before framing can begin)
  7. Formwork removal and backfill

Foundation work typically takes two to four weeks, including curing time. Concrete needs at least seven days to reach adequate strength, and most builders wait for 28-day strength tests on critical elements before applying full structural loads.

Phase 7: Framing and Structural Shell

Building the Skeleton

Framing is when your home first becomes recognizable. The skeletal structure of walls, floors, and roof takes shape, transforming a concrete foundation into a three-dimensional space you can walk through.

Framing in Bay Area custom homes typically uses one of two approaches:

  • Wood framing. The most common method. Engineered lumber (LVL beams, TJI joists, glulam columns) provides strength and dimensional stability. Wood framing is fast, flexible, and well-suited to residential construction.
  • Steel framing. Used for large spans, cantilevered elements, or contemporary designs with open floor plans. Steel allows wider openings and thinner structural profiles. It is more expensive than wood but enables architectural designs that wood alone cannot achieve.

Many Bay Area custom homes use a combination of both: steel moment frames for seismic resistance and open-concept living areas, with wood framing for standard walls, floors, and roof structure.

Framing Inspections

The building department conducts multiple inspections during framing:

  • Shear wall inspection. Verifying that lateral force-resisting elements (shear walls, hold-downs, anchor bolts) match structural plans.
  • Framing inspection. Checking wall stud spacing, header sizes, beam connections, floor joist installation, and roof framing.
  • Nailing inspection. Confirming that nailing patterns meet structural requirements, particularly in shear wall areas.

These inspections must pass before the project can proceed to the next phase. Failed inspections require corrections and re-inspection, which can add days or weeks.

Framing Timeline

Framing a typical 2,500 to 4,000 square foot custom home takes four to eight weeks. Larger homes, multi-story designs, and homes with complex rooflines or structural steel take longer. Weather can also affect the framing timeline; while Bay Area weather is generally favorable, rainy season (November through March) can cause intermittent delays.

Phase 8: Mechanical Systems (MEP Rough-In)

The Systems Behind the Walls

Once framing is complete and inspected, the mechanical, electrical, and plumbing (MEP) trades install their systems within the walls, floors, and ceilings. This is called “rough-in” because the systems are installed but not yet connected to fixtures or finished.

Plumbing Rough-In

Plumbers install supply lines (hot and cold water) and drain/waste/vent (DWV) piping. In a custom home, plumbing rough-in includes:

  • Main water supply and distribution
  • Hot water system (tank, tankless, or recirculating)
  • Drain lines for every fixture (sinks, toilets, showers, tubs, laundry)
  • Vent piping through the roof
  • Gas piping for cooktops, fireplaces, outdoor kitchens, and gas dryers
  • Radiant heating loops (if applicable)

Electrical Rough-In

Electricians run wiring for every circuit in the home:

  • Lighting circuits and switch locations
  • Outlet placement (including dedicated circuits for kitchen appliances, bathrooms, and home office)
  • Panel and sub-panel installation
  • Low-voltage wiring for data, audio, security, and home automation
  • Solar panel conduit and inverter connections (required by California code for new construction)
  • EV charger pre-wire or installation (increasingly standard in Bay Area homes)

HVAC Rough-In

HVAC contractors install ductwork, refrigerant lines, and equipment connections:

  • Supply and return ductwork throughout the home
  • Furnace and air handler placement
  • Condensing unit pad and line sets
  • Exhaust fans for bathrooms, kitchen, and laundry
  • Whole-house ventilation (required by code)
  • Zoning controls for multi-zone systems

MEP Inspections

Each trade requires a separate rough-in inspection before the walls can be closed:

  • Plumbing rough-in inspection (pressure test on supply lines, visual inspection of DWV)
  • Electrical rough-in inspection (wire sizing, box fill, grounding, GFCI/AFCI protection)
  • Mechanical (HVAC) rough-in inspection (duct sizing, equipment clearances, combustion air)

All three inspections must pass before insulation and drywall can begin. This is a critical gate in the construction sequence.

MEP Timeline

Mechanical rough-in typically takes four to six weeks, with the trades working in coordinated sequence. Plumbing usually goes first (since drain lines are gravity-dependent and least flexible in placement), followed by HVAC ductwork, then electrical wiring.

Phase 9: Insulation, Drywall, and Exterior Finishes

Closing the Envelope

Once all rough-in inspections pass, the home’s thermal and weather envelope is completed.

Insulation is installed in exterior walls, attic spaces, and any floors over unconditioned spaces. Bay Area homes typically use:

  • Fiberglass batt insulation (most common, cost-effective)
  • Spray foam insulation (superior air sealing, better for irregular cavities and complex framing)
  • Rigid foam board (often used on exterior walls for continuous insulation, which is increasingly required by California energy code)

An insulation inspection verifies compliance with Title 24 energy requirements before drywall can be hung.

Drywall (sheetrock) is hung, taped, mudded, and sanded to create smooth wall and ceiling surfaces. This process has multiple stages:

  1. Hanging: attaching drywall sheets to studs and ceiling joists
  2. Taping: embedding paper or mesh tape at seams
  3. Mudding: applying joint compound over tape and screw holes (three coats minimum)
  4. Sanding: smoothing the dried compound to a seamless finish
  5. Texturing (if applicable): most Bay Area custom homes use smooth, untextured walls

Exterior finishes are also installed during this phase:

  • Siding, stucco, stone, or other cladding
  • Windows and exterior doors (often installed earlier during framing for weather protection)
  • Roofing (also often installed during or immediately after framing)
  • Exterior trim, fascia, and soffits
  • Exterior painting or staining

This combined phase typically takes three to five weeks.

Phase 10: Interior Finishes and Fixtures

Where the Home Comes to Life

The finish phase is where your custom home transforms from a construction project into a living space. This is the longest and most detail-intensive phase of construction.

Finish Sequence

The order of interior finishes matters. Each trade builds on the previous one:

  1. Priming and first coat of paint. Walls and ceilings are primed and given a base coat before cabinetry and trim are installed, to protect surfaces and provide a clean backdrop.
  2. Cabinetry installation. Kitchen, bathroom, laundry, and built-in cabinetry is installed and leveled.
  3. Countertop templating and installation. After cabinets are in place, countertop fabricators template (measure) for a precise fit. Fabrication takes one to two weeks, followed by installation.
  4. Tile work. Bathroom floors and walls, shower enclosures, kitchen backsplashes, and any decorative tile applications.
  5. Hardwood flooring. Installed after most overhead work is complete to prevent damage. Includes sanding and finishing (for site-finished wood) or click-lock installation (for engineered pre-finished wood).
  6. Interior trim and millwork. Door casings, baseboards, crown molding, window trim, built-in shelving, and custom architectural details.
  7. Interior doors and hardware. Doors are hung, hinges adjusted, and hardware (knobs, levers, locks) installed.
  8. Plumbing fixtures. Sinks, faucets, toilets, shower heads, tub fillers, and other plumbing trim.
  9. Electrical fixtures. Light fixtures, switches, outlets, and cover plates.
  10. Appliance installation. Kitchen appliances, laundry equipment, HVAC thermostats, and specialty items.
  11. Final paint. Touch-ups and final coat on all painted surfaces.
  12. Final cleaning. Professional construction cleaning of the entire home.

Finish Phase Timeline

Interior finishes typically take six to twelve weeks depending on the complexity of the design and the number of custom elements. Homes with standard finishes and straightforward layouts finish faster. Homes with custom millwork, specialty tile work, and imported materials take longer.

The finish phase is also where material lead times matter most. Items like custom cabinetry (8-12 weeks), natural stone countertops (3-4 weeks for fabrication), specialty tile (varies widely), and imported fixtures can create scheduling bottlenecks if not ordered well in advance. This is another advantage of completing all material selections during the design phase: materials can be ordered months before they are needed.

Phase 11: Final Inspections

The Approval Process

Before you can occupy your new home, it must pass a final inspection from the local building department. The final inspection confirms that the completed construction matches the approved plans and complies with all applicable building codes.

The inspector reviews:

  • Structural elements (visible framing connections, hold-downs, foundation bolts)
  • Plumbing (fixture connections, water heater, gas shutoff)
  • Electrical (panel, GFCI/AFCI protection, smoke and CO detectors)
  • HVAC (equipment installation, duct connections, thermostat operation)
  • Fire safety (smoke detectors, carbon monoxide detectors, fire sprinklers if required)
  • Energy compliance (insulation, window labels, HVAC efficiency, solar panels)
  • Accessibility (where applicable)
  • Exterior (drainage, grading, setbacks)

If the inspector finds issues, they issue a correction notice. The builder addresses the corrections and schedules a re-inspection. Most Custom Home projects pass final inspection on the first visit because our field supervision team conducts an internal quality inspection before requesting the city’s final.

Certificate of Occupancy

Once the home passes final inspection, the building department issues a Certificate of Occupancy (C of O). This document certifies that the home is safe to live in and complies with all codes. You cannot legally move in without it, and your lender will not release final construction loan funds without it.

Phase 12: Landscaping and Exterior Finishes

Completing the Property

Landscaping often runs in parallel with the final stages of interior construction. Depending on the scope, it may begin as soon as the exterior of the building is complete.

Landscaping for a custom home typically includes:

  • Hardscape: Driveway, walkways, patios, retaining walls, outdoor kitchen structures
  • Softscape: Lawn, plantings, trees, ground cover, mulch
  • Irrigation: Automated sprinkler and drip irrigation systems
  • Drainage: Surface drainage, French drains, area drains
  • Outdoor lighting: Path lights, accent lighting, security lighting
  • Fencing and gates
  • Pool and spa (if applicable; this is a separate permit and has its own timeline)

Bay Area landscaping should account for drought-tolerant planting requirements. Most jurisdictions require water-efficient irrigation and limit the percentage of lot area that can be planted with traditional turf grass.

Landscaping typically takes two to six weeks, depending on scope. Hardscape elements (concrete, pavers, retaining walls) must be completed before planting begins.

Phase 13: Move-In

The Final Walk-Through

Before move-in, you do a final walk-through with your builder. This is the punch list inspection, where you document any remaining items that need attention:

  • Paint touch-ups
  • Cabinet and door adjustments
  • Hardware alignment
  • Minor trim corrections
  • Cleaning touch-ups
  • Appliance demonstrations and manuals

Custom Home schedules a formal walk-through and documents every item. Our commitment is to resolve all punch list items before you move in, not after.

What You Receive at Move-In

On move-in day, your builder should provide:

  • Certificate of Occupancy
  • All warranty documentation (builder warranty, manufacturer warranties for appliances, roofing, windows, HVAC, etc.)
  • Operation and maintenance manuals for mechanical systems
  • As-built plans showing the home as constructed
  • Spare materials (paint for touch-ups, extra tile, flooring pieces)
  • Utility account information and transfer instructions
  • A list of all subcontractors and suppliers (for future service needs)

How Custom Home’s Two-Phase Process Streamlines the Timeline

The process described above applies to every custom home project, regardless of the builder. What differs is how well-organized and transparent the process is.

Custom Home’s two-phase approach separates the process into two clear commitments:

Phase 1: Design, Engineering, and Budgeting. This covers everything from the initial consultation through completed construction documents, 3D renderings, material selections, and an itemized scope of work. Phase 1 has its own fee and its own deliverables. At the end of Phase 1, you know exactly what your home will look like, what it will cost, and how long it will take. You then decide whether to proceed.

Phase 2: Construction. Once you approve the Phase 1 deliverables and sign the construction contract, building begins from fully-developed plans with locked-in pricing. Because every material was selected and every detail was resolved during Phase 1, construction proceeds without the change orders, indecision delays, and budget surprises that plague traditionally-managed projects.

This separation matters because it gives you an informed exit point. If the design process reveals that your vision exceeds your budget, you can adjust the scope before construction begins, not after you have already spent hundreds of thousands of dollars. You own all the Phase 1 documents and can use them however you choose.

Custom Home Design and Build holds CSLB license #986048 and has been building custom homes across the Bay Area since 2005. Our experience with local jurisdictions, engineering requirements, and construction conditions means we can anticipate and manage the challenges that are unique to building in this region.

Common Mistakes That Derail Custom Home Projects

Understanding the process is important. Understanding what can go wrong is equally important. Here are the mistakes we see most often:

Rushing Through Design

Homeowners who are eager to start building sometimes push through the design phase without fully resolving their priorities. This leads to change orders during construction, which cost 15-30% more than the same decision would have cost during design.

Underestimating Permitting Timelines

Bay Area permitting can take two to six months. Homeowners who expect a two-week turnaround are setting themselves up for frustration. Build permitting time into your project schedule from day one.

Not Ordering Materials Early Enough

Custom cabinetry takes 8-12 weeks. Specialty windows can take 10-16 weeks. Natural stone and imported tile have unpredictable lead times. If materials are not ordered during the design phase, construction will stall while you wait for deliveries.

Choosing a Lot Without a Feasibility Study

A beautiful lot with a stunning view may also have unstable soil, protected trees, a steep slope requiring extensive grading, or zoning restrictions that limit your buildable area. Always conduct a feasibility study before purchasing.

Hiring Separate Architect and Contractor Without Understanding the Risks

The traditional model of hiring an architect first and then bidding the plans to contractors creates a gap where no one takes full responsibility for both design intent and construction reality. This gap is where cost overruns and timeline delays live. Design-build eliminates this gap.

Your Next Step

Building a custom home is a significant undertaking, but it does not have to be overwhelming. The right builder and the right process make the difference between a stressful experience and a rewarding one.

If you are considering a custom home in the Bay Area, the best first step is a conversation. We will discuss your vision, review your lot (or help you evaluate one), and explain how our two-phase process works for your specific situation. There is no obligation and no pressure.

Contact Custom Home for a free consultation to start the conversation about your custom home project.

Frequently Asked Questions

How long does it take to build a custom home from start to finish?

The total timeline for a custom home ranges from 14 to 24 months, including pre-construction and construction. The pre-construction phase (lot selection, design, engineering, permitting) takes 6 to 12 months. Active construction takes 10 to 14 months for a typical Bay Area home. Projects with hillside lots, complex designs, or slow-permitting jurisdictions can extend this timeline.

What is the most important step in the custom home building process?

The design phase is the most important step because every decision made here affects cost, timeline, and final quality. Completing all design decisions, material selections, and engineering before construction begins eliminates the change orders and mid-build surprises that cause 80% of budget overruns. Custom Home's Phase 1 process is dedicated entirely to getting this right.

Do I need to own land before hiring a custom home builder?

Not necessarily. Many design-build firms, including Custom Home, can help you evaluate potential lots for buildability, zoning compliance, and hidden costs before you purchase. Starting the builder relationship early often saves money because you avoid buying a lot with expensive site challenges you did not anticipate.

What permits are required to build a custom home in the Bay Area?

At minimum, you need a building permit, grading permit (for site work), and utility connection permits. Many Bay Area jurisdictions also require design review, environmental review, tree removal permits, and Title 24 energy compliance documentation. Permitting timelines vary by city. San Jose typically processes permits in 4-8 weeks, while cities like Palo Alto and Los Gatos can take 3-6 months for plan review.

What is a design-build approach and why does it matter for custom homes?

Design-build means one company handles both the design and the construction under a single contract. This eliminates the coordination gaps that occur when an architect and contractor work independently. For custom homes, design-build delivers faster timelines (up to 33% shorter), better cost control, and a single point of accountability. Custom Home uses a two-phase design-build model where Phase 1 (design) and Phase 2 (build) are clearly separated so you approve everything before construction begins.